City releases sewer system construction schedule

1056
0
Share:

The City of Liberty Hill announced this week that the third construction phase of the city’s sewer system has begun with the main line from the lift station to RR 1869 already substantially complete.

Qro Mex Construction will be progresing with the project according to the following schedule:

Feb. 13-24: Installing sewer lines along Snyder’s Trail, including services, manholes, and road and driveway repairs.

Feb. 27-March 9: Installing sewer lines along the full length of Bryson Bend including services, manholes, and road and driveway repairs.

March 12-23: Installing sewer lines on Bluebonnet Lane and from Bluebonnet along RR 1869 to Snyder’s Trail, including services, manholes, and road and driveway repairs.

March 26-April 6: Installing sewer lines along RR 1869 from State Highway 29 to Snyder’s Trail, including services, manholes, road bores, and road and driveway repairs.

City staff say the dates may vary with weather conditions and other unforeseen factors.

For more information concerning the sewer construction, please contact Qro Mex from 8 a.m. to 5 p.m. Monday through Friday at (830) 598-2268.